Pavement Management Program

A program of pavement management requires an accurate inventory and current condition rating of every street in the city. In 2017, the City of Peoria commissioned an electronic data collection to verify inventory and provide an assessment of every segment of road. Infrastructure Management Services (IMS) is a company with extensive experience in pavement management throughout the country. They conducted the electronic survey of the roadways and provided the data to the city.

The data is expressed as a numerical factor, known as a pavement condition index (PCI), which rates the surface condition of the road on a scale from 0-100, 0 being the worst and 100 being the best possible condition. This information was entered into our pavement management software to help establish a budget-based prioritization of projects for the next several years. You can view the FY17 Pavement Management Executive Report (PDF), the City’s Five-Year Project Plan (PDF) and the complete citywide list of street-by-street PCI (PDF) by clicking either of the links provided.

Annual Peoria Streets Improvement Projects

The Surface Treatment Projects scheduled throughout each fiscal year consist of slurry seal, chip seal, micro seal and seal coat applications. (Please note: Applications will vary within each referenced neighborhood). The city's contractor will notify the affected homes with door hangers in advance of the work being performed. Specific instructions will be provided on the door hanger.

Early Waste Collection Notice

All pavement treatments applied to roadways in the warmer months will receive early morning trash pickup for at least 30 days after construction is complete. These early pickups are necessary in an effort to preserve and prevent damage to the treatments. By getting the heavy trucks through in the cooler hours, we can help protect the tender new surface. If pavement preservation work is occurring on your street, please have your trash container on the street by 6 a.m. on your designated waste collection day and continue such practice for the following four weeks after the project is complete. The City of Peoria Streets Division appreciates your cooperation in our efforts to deliver the best possible results.

If you have questions, please call Peoria's Streets Division at (623) 773-7432.


CURRENT PROJECTS

ADA Sidewalk Ramp Improvements on Williams Road

On Monday, November 19, 2018, City of Peoria Contractor, Bunney’s Inc., will begin implementing ADA Sidewalk Ramp Improvements on Williams Road, just west of 107th Avenue. There will be a 24-hr eastbound lane closure on Williams Road, between 107th Avenue and 108th Avenue. Detour routes will be provided to maintain access for residents, businesses, and emergency vehicles. This work has been scheduled during fall break to avoid disrupting traffic operations for the nearby elementary school. Sidewalk improvements at this location are projected to be complete on Wednesday, November 21, 2018. 

FY19 75th Avenue Mill & Overlay (Grand Avenue to Northern Avenue)

On Monday, November 26, 2018, City of Peoria Contractor, Nesbitt Contracting, will be begin a mill and overlay project on 75th Avenue, from Grand Avenue to Northern Avenue. There will be 24-hour lane and left-turn restrictions throughout this project area; however, at least one lane of traffic will remain open in each direction on 75th Avenue. Access to side streets and driveways may be restricted at times; however, the contractor will make accommodations as necessary.

Additionally, from December 3-6, 2018, Golden Lane will be CLOSED from 77th Avenue to 75th Avenue, while crews complete paving operations on 75th Avenue. Construction activities will take place during daytime hours, Monday through Friday; and the anticipated project completion date is December 19, 2018. Residential communities and business owners near this project area will receive additional information related to this project. View Detour Map Around Project Area.  

FY19 Parking Lot Asphalt Replacements

On Tuesday, November 27, 2018, City of Peoria Contractor, TALIS Construction, will begin parking lot asphalt replacements in the Parks shown below. Parking lots will be restricted while the work occurs. Construction hours will be from 7:00 am to 5:00 pm, Monday through Friday, excluding holidays. This work is projected to be complete on Friday, December 28, 2018. 

Project Areas

  • Alta Vista Park
  • Fletcher Heights Park
  • Deer Village Park
  • Ira Murphy Park
  • Sunnyslope Park

FY19 Large Crack Repair Project - Communities South of Bell Road Corridor

On Tuesday, November 27, 2018, City of Peoria Contractor, ViaSun Corporation, will begin large crack repairs in areas bound by Kelton Lane, Betty Elyse Lane, 91st Avenue and 86th Avenue. There will be lane restrictions throughout this project area; however, at least one lane of traffic will remain open in each direction while the contractor completes this work. Construction hours will be from 8:30 am to 5:00 pm, Monday through Friday; and the anticipated project completion date is Friday, December 14, 2018. Please note residents within this project area will receive additional information prior to any work occurring on his or her street. View Map of Project Area (PDF).

FY19 ADA Sidewalk Ramp & Concrete Improvements - 107th Avenue (Beardsley Road to Williams Road)

On Tuesday, November 13, 2018, City of Peoria Contractor, Bunney’s Inc., will begin implementing ADA Sidewalk Ramp Improvements on 107th Avenue, from Beardsley Road to Williams Road. There will be 24-hr slow-lane restrictions on 107th Avenue; however, the contractor will maintain access for residents, businesses, and emergency vehicles. Please note the contractor will only restrict one lane at a time. Once the concrete repairs on the west side of the road are complete, repairs will commence on the east side of 107th Avenue. This project is expected to be complete in January.

FY19 Crack Seal Project 

On Wednesday, November 7, 2018, City of Peoria Contractor, Vincon, will begin implementing a crack seal treatment on the areas bound by: Bell Road, Kelton Lane, 84th Avenue and 91st Avenue. Construction hours will be from 9:00 pm to 5:00 am. There will be lane restrictions throughout this project area; however, the contractor will maintain access to residents, businesses, and emergency vehicles. These repairs are expected to be complete by early morning hours on Saturday, November 10, 2018.

Then on Tuesday, November 13, 2018, Vincon will begin crack seal treatments in communities south of Kelton Lane. See attached map. Construction hours will be from 7:00 am to 5:00 pm, Monday through Friday, excluding holidays. There will be lane restrictions throughout this project area as well; however, the contractor will maintain access as needed. Repairs are expected to be complete in January. View Map of Project Area. 

FY19 Mill & Overlay

In the coming months, the City of Peoria Streets Division anticipates working with a third party contractor to complete a mill and overlay in the areas shown below. There will be lane restrictions throughout this project area; however, the contractor will maintain access for residents, businesses, and emergency vehicles. Construction times will be from 8:00 am to 4:30 pm, Monday through Friday, excluding holidays. Additional details related to this project will be provided, as we approach the start date.

  • 91st Avenue, from Bell Road to Union Hills Road
  • 75th Ave, from Northern Avenue to Olive Avenue

FY19 COMPLETED Street Projects:

FY19 Large Crack Repair

FY19 Mill & Overlay

FY19 ADA Ramp Improvements

FY19 Slurry Seal Pavement Preservation Treatments

FY18 Completed Projects Map

Learn more about pavement preservation. (PDF)

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer