HAPPY VALLEY ROAD
Project
Description
This project will provide a
vital east-west link for northern Peoria by constructing the
missing segment of Happy Valley Road over the New River between
Lake Pleasant Parkway and 75th Avenue. This new link to Peoria's
street network will also provide additional options for traffic
now using Lake Pleasant Parkway, 83rd Avenue, 67th Avenue, and
Deer Valley Road. The improvements will include one lane of
roadway in each direction plus bike lanes, street lighting,
landscaping, drainage, and a 16-inch waterline. The pavement
will ultimately serve as the three westbound lanes of what will
become a six-lane roadway.
Project at a Glance
|
Lead Agency |
City of Peoria
Chris Kmetty (Peoria Project Manager)
Phone: 623-773-7247
E-mail:
Chris.Kmetty@PeoriaAz.Gov |
|
Design Consultant |
Parsons |
|
Contractor |
N/A |
|
Project Budget |
$35,899,430 |
|
Funding Sources |
|
Project
Status
The
final design plans were completed July 2006. The City is now in
the process of acquiring the necessary land for the roadway.
Funding for construction is available in fiscal years 2008 and
2009.
|
Design |
100% |
|
|
Land
Acquisition |
30% |
|
|
Construction |
0% |
|