|

67TH AVENUE INTERIM WIDENING
Project
Description
67th Avenue, between Pinnacle Peak Road and Happy Valley Road,
is a two-lane roadway with various segments improved by adjacent
development to four lanes. Traffic volumes on this segment
exceed the allowed capacity of a two-lane roadway. This project
provides for the construction of temporary pavement to widen
this segment of 67th Avenue to five lanes (one additional lane
in each direction and a center turn lane). These improvements
will provide immediate relief from traffic congestion until the
permanent improvements are constructed in the future.
Project at a Glance
|
Lead Agency |
City of Peoria
Richard Costa (Peoria Project Manager)
Phone: 623-773-7951
E-mail:
Richard.Costa@PeoriaAz.Gov |
|
Partner Agency |
Maricopa County
Department of Transportation (MCDOT)
Samir Hatab (MCDOT Project Manager)
Phone:
602-506-2867 |
|
Design Consultant |
Maricopa County
Department of Transportation (MCDOT) |
|
Contractor |
Centennial
Contractors, Inc.
24-Hour
Construction Hotline: 602-264-6416 |
|
Project Budget |
$970,000 |
|
Funding Sources |
|
Project
Status
Construction began on October 11, 2006 on the
east side of 67th Avenue. The west side of 67th Avenue
will follow the east side beginning in late October.
Construction will be completed by December 2006. Traffic
restrictions will be in place throughout construction, so
motorists should allow extra time for travel in this area.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
15% |
|
Links
Last
Updated:
Thursday November 09, 2006 11:32 AM
|