STONE WELL SITE REHABILITATION (UT00289)
 |
Financed by
the
Water Infrastructure Finance Authority of Arizona and
the American Recovery and Reinvestment Act (ARRA) |
 |
| |
|
|
Program:
The funding for this
work was made possible through the Water Infrastructure Finance
Authority (WIFA) of Arizona and the American Recovery and
Reinvestment Act (ARRA) of 2009. This project will help
put people back to work and potentially create new jobs.
Project
Description:
The City of Peoria awarded a contract to Felix Construction Company
to complete necessary upgrades to the Stone Well Site. These
upgrades will consist of electrical, mechanical, security, and
general site improvements necessary to bring the aging site up to
current City standards.
Project at a Glance
|
Lead Agency |
City of Peoria
Daniel Kiel (Peoria Utilities Project Manager)
Phone: 623-773-7982
E-mail:
Daniel.Kiel@peoriaaz.gov |
|
Design Consultant |
Brown and Caldwell |
|
Contractor |
Felix Construction |
Project Budget
(Construction) |
$1,374,734.00 |
|
Funding Sources |
WIFA / ARRA |
Project
Status:
Construction on site began in July 2009, and is scheduled for
completion in June 2010.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
75% |
|
LINKS:
Public Notification
Exhibit
PPT
Road Closures and Lane Restrictions
Updated
April 19,