99th AVENUE AND ROSE GARDEN WELL EQUIPPING (UT00288)
Program:
The funding for this work was made possible through the
Water Infrastructure Finance Authority (WIFA) of Arizona and
the American Recovery and Reinvestment Act (ARRA) of 2009.
This project will help put people back to work and
potentially create new jobs.
Project
Description:
The City of Peoria awarded a contract to Felix
Construction Company to equip the well site, located south of
Lake Pleasant Parkway and west of 99th Avenue.
Improvements will include the installation of new well
equipment, construction of a block wall and landscaping for
the site.
Project at a Glance
|
Lead Agency |
City of Peoria
Daniel Kiel (Peoria Utilities Project Manager)
Phone: 623-773-7982
E-mail:
Daniel.Kiel@peoriaaz.gov |
|
Design Consultant |
Stanley Consultants |
|
Contractor |
Felix Construction |
Project Budget
(Construction) |
$1,387,822.00 |
|
Funding Sources |
WIFA / ARRA |
Project
Status:
Construction on site is underway and is expected to be completed
in June 2010.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
50% |
|