NEW RIVER TRAIL - NORTHERN AVENUE TO OLIVE AVENUE
(CS00125)
Project
Description
This project is a
one-mile trail on the west bank of New River, located between
Olive Avenue and Northern Avenue. The project includes a
10-foot wide path and landscaping along the entire section. The
path is partially funded in FY12 with TERC funding through ADOT.
The project may also include an underpass at Northern Avenue,
and a low water crossing structure to connect into the Glendale
Regional Trail along New River. Coupled with this project in
FY11 is the development of a trailhead, located at Olive Avenue,
to provide off street parking and comfort services along the
path. The project is requested in FY11 by utilizing Federal
stimulus funding entirely. Future year funding utilizes a
combination of Federal funds and matching funds from City of
Peoria sources. Design of the trail and landscaping of the
one-mile trail segment is complete.
Project at a Glance
|
Lead Agency |
City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7125
Email:
karl.zook@peoriaaz.gov |
|
Design Consultant |
Aztec Engineering,
Inc. |
|
Project Budget |
$700,000.00 |
Project
Status
The design for
the new trail and underpass is anticipated to begin in early
May. The City and the State of Arizona will work together
with the design consultant to ensure the plans are ready for a
contractor by the spring of 2013.
|
Design |
0% |
|
|
Construction |
0% |
|
Updated: April
10, 2012
|