COTTON CROSSING - PHASE II IMPROVEMENTS
Project
Description
This project is the second phase of a joint
effort project between the City of Peoria and a private
developer (Wal-Mart) to extend the existing recently constructed
six-lane Cotton Crossing arterial roadway south, crossing the
Burlington Northern Santa Fe (BNSF) Railroad tracks and
intersecting with Grand Avenue.
The new Cotton Crossing/Grand Avenue intersection will be a
signalized intersection, owned and maintained by the Arizona
Department of Transportation. In addition, roadway improvements
to Grand Avenue will be required at this intersection to account
for new turn lanes and roadway pavement grade adjustments.
Furthermore, in cooperation with another developer, Cotton
Crossing has been extended southwesterly, from Grand
Avenue, connecting to the existing 83rd Avenue/Mountain View
Road intersection. That project is complete.
Project at a Glance
|
Lead Agency |
City of Peoria
Richard Costa (Peoria Project Manager)
Phone: 623-773-7951
E-mail:
Richard.costa@peoriaaz.gov
|
|
Design Consultant |
Kimley-Horn
Associates |
|
Contractor |
Nesbitt
Contracting |
Project
Status
The eastbound lanes of Grand Avenue are complete.
The contractor is currently preparing to install signing and
striping. BNSF Railroad is currently installing railroad
equipment at the upgraded roadway crossing. Completion is
scheduled for mid-May 2010.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
98% |
|
Updated April 20,
2010