Project Description
This project provides for the study, design, construction and post design services required to construct a privacy wall along the south side of Union Hills Drive, between 83rd Avenue and 84th Avenue.  This project also includes installation of landscape along the south side of Union Hills Drive, between 84th Avenue and 83rd Avenue, and between the wall and the back of the sidewalk.

Project at a Glance

Lead Agency City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7260
E-mail: Karl.Zook@Peoriaaz.gov
Design Consultant Parsons Brinckerhoff
Contractor FNF Contractors
Project Budget $4,500,000.00
Funding Source MDA Bond Street System

Project Status
The project design is 100% complete.  The contractor awarded for construction is Land-Tech Landscape Construction.  The wall construction is anticipated to take place between March 2010 and July 2010.

Design 100%
25% 50% 75% 100%
                                       
Land Acquisition 100%
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     