 91st Avenue and Olive Avenue Intersection Improvements

Project Description
This project includes design, ROW, construction, and construction administration in two phases for interim and ultimate capacity improvements to the intersection and vicinity to accommodate additional turn lanes (both right and left), and additional through lanes determined through an analysis and projection of traffic data.  Improvements will include: paving, curb, gutter, driveways, medians, pavement marking, signing and striping, street lighting, sidewalks, pedestrian access ramps, landscaping, landscape irrigation and utility relocations.  The traffic signal will be relocated and modified to direct additional turn lanes and thru lanes.  Traffic signal interconnect conduit and related facilities will be included in the project.

Project at a Glance

Lead Agency

Arizona Department of Transportation (ADOT)

Partner Agency City of Peoria
Ben Wilson (Project Manager)
Phone: 623-773-7185
E-mail: Ben.Wilson@PeoriaAz.gov
Design Consultant Kimley-Horn & Associates
Contractor N/A
Project Budget $3.7 Million
Funding Sources General Obligation Bonds

Project Status as of November 2008
The widening project is anticipated to start in the Spring, 2009.  Utilities, such as SRP Irrigation, SRP Power, APS Power, Southwest Gas and Cox Communications will be relocated during the year, 2008.  These utilities need to be relocated before the widening construction can occur.

There will be on-and-off construction activities beginning from July 2008 through February 2009 prior to the intersection pavement widening.  Lane restrictions will be limited to night-time when possible.

Agreement with ADOT to administer construction is being sent to Council on December 2, 2008.  Approval will allow ADOT to advertise for the intersection widening construction.

Activity

 

Anticipated Activity Duration

 

Progress of Activity

 

Intersection Widening Design

Completing Design Documents for submittal to ADOT

100%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

COX relocations

Relocated as of April 2008

100%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Activities above must be completed before Activities below can start

Southwest Gas relocation

Expect relocation to be completed by October 10, 2008

100%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Land Acquisition

Finalizing Land Acquisition

99%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

City waterline relocations

Relocations to be complete November 12, 2008. 

Minimal traffic restrictions. 

Water lines and hydrants need to be moved prior to SRP Irrigation can relocate

95%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Activities above must be completed before Activities below can start

SRP Power relocation

Anticipate relocation work in November, 2008

0%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

APS Power relocation

APS has relocated.

No lane restrictions expected

100%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Activities above must be completed before Activities below can start

SRP Irrigation relocation

November 2008 – February 2009

0%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Activities above must be completed before Activities below can start

Intersection Widening Construction

April 2009 to December 2009

0%

25%

50%

75%

100%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Download Documents

Last Updated: Friday November 07, 2008 01:19 PM

 