75th AVENUE AND THUNDERBIRD ROAD INTERSECTION
IMPROVEMENTS (EN00089)
Project
Description
75th Avenue
and Thunderbird Road is the fifth busiest intersection in the
City of Peoria. Currently, the two lanes in each direction,
with single left-turn lanes, has been causing longer delays and
the traffic engineers have concluded that the intersection needs
to be improved to maintain traffic flow. This project will
widen the intersection to include three through lanes in each
direction, with dual left-turn lanes. There will also be a bike
lane and new sidewalks. Other improvements include upgraded
lighting, raised medians and improved signal equipment to
enhance the safety of the intersection.
Project at a Glance
|
Lead Agency |
City of Peoria
Geoffrey Zinnecker (Peoria Project Manager)
Phone: 623-773-7212
E-mail:
Geoffrey.zinnecker@peoriaaz.gov |
|
Design Consultant |
Michael Baker
Jr. Corp |
|
Contractor |
FNF Construction |
|
Project Budget |
$6.5M |
|
Funding Sources |
General
Obligation Bonds |
Project
Status
SRP
relocated the large irrigation structure on the
southwest corner and completed February 2012.
SRP Electric
relocated overhead and underground lines to
accommodate the wider road and completed March 2012
16" water line is
being installed along 75th Avenue. Expect traffic restrictions
through April 2012.
|
Design |
100% |
|
|
Land
Acquisition |
93% |
|
|
Utility
Relocation |
95% |
|
|
Construction |
15% |
|
Construction Update
Updated April 11, 2012 |