75th AVENUE AND THUNDERBIRD ROAD INTERSECTION IMPROVEMENTS (EN00089)

Project Description
75th Avenue and Thunderbird Road is the fifth busiest intersection in the City of Peoria.  Currently, the two lanes in each direction, with single left-turn lanes, has been causing longer delays and the traffic engineers have concluded that the intersection needs to be improved to maintain traffic flow.  This project will widen the intersection to include three through lanes in each direction, with dual left-turn lanes.  There will also be a bike lane and new sidewalks.  Other improvements include upgraded lighting, raised medians and improved signal equipment to enhance the safety of the intersection.

Project at a Glance

Lead Agency City of Peoria
Geoffrey Zinnecker (Peoria Project Manager)
Phone: 623-773-7212
E-mail:
Geoffrey.zinnecker@peoriaaz.gov
Design Consultant Michael Baker Jr. Corp
Contractor FNF Construction
Project Budget $6.5M
Funding Sources

General Obligation Bonds

Project Status
SRP relocated the large irrigation structure on the southwest corner and completed February 2012.

SRP Electric relocated overhead and underground lines to accommodate the wider road and completed March 2012

16" water line is being installed along 75th Avenue. Expect traffic restrictions through April 2012.

Design 100%
25% 50% 75% 100%

 

                                     
Land Acquisition 93%
25% 50% 75% 100%

 

                                     
Utility Relocation 95%
25% 50% 75% 100%

 

                                     
Construction 15%
25% 50% 75% 100%

 

                                     

Construction Update

Updated April 11, 2012