Community Park Number 2

Project Description
Construction of an 80-acre Community Park, located at the southeast corner of 83rd Avenue and Olive Avenue.

Project at a Glance

Lead Agency City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7260
E-mail:
karl.zook@peoriaaz.gov
Partner Agency

N/A

Contractor Haydon Contracting
Project Budget $17.6 million
Funding Source Bonds and Half-Cent Sales Tax

Project Status
The master plan can be viewed via the attached link below.  This master plan alternative was built on a series of public meetings and feedback from stakeholder meetings.  The next steps include completion of the site plan and completion of the design documents, which will occur over the next year.   This project will be coordinated with street and drainage improvements on 83rd Avenue, between Mountain View Road and Butler Road, in order to minimize disruption to adjacent neighborhoods.

Design 20%
25% 50% 75% 100%

 

                                     
Land Acquisition 100%
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     