| Project Phase | Consultant / Contractor | % Complete |
| Design: | GHD Engineering | 100% |
| Construction: | Felix Construction | 80% |
Project Description
This project will construct a pressure reducing valve (PRV) within the right of way inside a vault on the west side of 91st Avenue. The PRV will allow water to pass from Zone 3E to Zone 2E in the water distribution system. This site will improve water flow in the area and act as a redundant water source to the customers in Zone 2E.
Project Status
Mechanical improvements are complete. Power to site will be provided by solar panels.
Latest Public Engagement
No public meetings have taken place. Informational site sign will be posted along 91st Avenue. |