Program: The funding for this work was made possible through the Water Infrastructure Finance Authority (WIFA) of Arizona and American Recovery and Reinvestment Act (ARRA) of 2009. These projects will help put people back to work and potentially create new jobs. Project Scope: Capital Improvement Project UT00294 (Section C) will repair approximately 3,800 feet of 36-inch sewer line and ten (10) manholes on 95th Avenue, between Northern and Peoria Avenues. The repairs will consist of installing a cured-in-place-pipe (CIPP) liner and will require installing bypass pumps to divert all of the sewer flows in the line while the repairs are being made. Project at a Glance
Project Schedule: June 2009 through October 2009 PROJECT STATUS October 31, 2009
24 Hour Construction
Hotline: 602-264-6416
Public
Notice
|