24" Waterline Beardsley and 91st Avenues UT00145

Financed by the
Water Infrastructure Finance Authority of Arizona and The American Recovery and Reinvestment Act (ARRA)

Program:  The funding for this work was made possible through the Water Infrastructure Finance Authority (WIFA) of Arizona and American Recovery and Reinvestment Act (ARRA) of 2009.  These projects will help put people back to work and potentially create new jobs.

Project Scope:  Construct 3 miles of 24" water transmission line. This project is being constructed along with storm drain improvements along 91st Avenue and Beardsley Road. The 24" waterline will be installed in 91st Avenue between Union Hills Drive and Beardsley Road and in Beardsley Road between 87th Avenue and Lake Pleasant Road. (Learn more about that project.)

Project at a Glance

Lead Agency City of Peoria
Leisa Burdine (Peoria Utilities Project Manager)
Phone: 623-773-7297
E-mail:
Leisa.Burdine@peoriaaz.gov
Engineer Strand Associates, Inc.
Contractor Pulice Construction
Project Budget
(Construction)
$5,470,024.00
Project Delivery Construction Manager At Risk

Project Schedule:  April 30, 2009 through March 30, 2010

PROJECT STATUS

September 30, 2009

  • 100% Drawings completed

  • Contract GMP completed

  • ATC has been issued by MCESD

  • Council approved at April 21, 2009 Council Meeting

  • NTP issued May 11, 2009

  • Contractor mobilized June 1, 2009

  • Contractor is 70% complete with waterline installation