VISTANCIA RECHARGE WELLS 1 AND 2 (VIS0015)
Project
Description
This project will construct
Vadose Zone Recharge Wells Nos. 1 and 2, which will recharge A+
quality effluent from the City of Peoria Jomax Water Reclamation
Facility (WRF) during periods of low demand within the reclaimed
water system. The primary components of the project include:
-
800 feet of 8”
diameter DIP reclaimed water line.
-
12-foot wide compacted
gravel access roadway through the site
-
Two 12-inch diameter
injection
wells approximately 150’ in depth.
-
Two
below grade
pre-cast concrete vaults with control and metering equipment.
-
One four-inch
diameter
monitoring well approximately 800-feet deep.
Project at a Glance
|
Lead Agency |
City of Peoria
Joe Kurrus (Peoria Project Manager)
Phone: 623-773-7753
E-mail:
joe.kurrus@peoriaaz.gov |
|
Design Consultant |
Wilson Engineers |
|
Contractor |
MGC Contractors, Inc. |
|
Project Budget |
$700,000 |
|
Funding Source |
VCFD |
Project
Status:
Construction is underway. Recharge wells 1 and 2 have been
completed. The monitoring well has been completed.
On-going site work will continue in March. Electrical site
work and primary power will be installed in April.
Project completion is expected in May 2012.
|
Design |
100% |
|
|
Construction |
60% |
|
Updated April 11, 2012
|