VISTANCIA RECHARGE WELLS 1 AND 2 (VIS0015)

Project Description
This project will construct Vadose Zone Recharge Wells Nos. 1 and 2, which will recharge A+ quality effluent from the City of Peoria Jomax Water Reclamation Facility (WRF) during periods of low demand within the reclaimed water system.  The primary components of the project include:

  • 800 feet of 8” diameter DIP reclaimed water line.

  • 12-foot wide compacted gravel access roadway through the site

  • Two 12-inch diameter injection wells approximately 150’ in depth.

  • Two below grade pre-cast concrete vaults with control and metering equipment.

  • One four-inch diameter monitoring well approximately 800-feet deep.

Project at a Glance

Lead Agency City of Peoria
Joe Kurrus (Peoria Project Manager)
Phone: 623-773-7753
E-mail: joe.kurrus@peoriaaz.gov
Design Consultant Wilson Engineers
Contractor MGC Contractors, Inc.
Project Budget $700,000
Funding Source VCFD

Project Status:
Construction is underway.  Recharge wells 1 and 2 have been completed.  The monitoring well has been completed.  On-going site work will continue in March.  Electrical site work and primary power will be installed in April.  Project completion is expected in May 2012.

Design 100%
25% 50% 75% 100%
                                       
Construction 60%
25% 50% 75% 100%

 

                                     

Updated April 11, 2012