Westbrook Village Storm Drain and 24-inch Waterlines

Project Description
Phase 1 of this project is for the installation of storm drains and 24" diameter waterlines in 91st Avenue from Union Hills Drive to Beardsley Road and in Beardsley Road from 87th Avenue to 95th Avenue.  Both roadways will be restored with a pavement overlay over the same limits of construction.

Additionally, in phase 2, there will be an extension of the 24" diameter in Beardsley Road from 95th Avenue to Lake Pleasant Road.  The roadway restoration will be a replacement of the disturbed areas.  The subsequent Beardsley Road Project (11) will address a comprehensive pavement reconstruction.  

Project at a Glance

Lead Agency City of Peoria
Burton Charron, P.E. (Project Manager)
Phone: 623-773-7237
E-mail: Burton.charron@PeoriaAz.gov
Design Consultant Entellus \ Brooks Strand Associates
Contractor To Be Determined
Project Budget $11 Million
Funding Sources
  • General Obligation Bonds

  • Water Revenue Bonds

  • Water Expansion Fees

  • Water Utility Fees

Project Status
Currently, the design is being finalized and the project is soliciting Construction Managers for construction of the project.  Construction is proposed to begin in January 2009 and proposed to be completed in the Fall 2009.  Utility relocation work has commenced and will continue to be underway through January 2009, the beginning of construction. 

Design 95%
25% 50% 75% 100%

 

                                     
Land Acquisition 100%
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     