Westbrook
Village Storm Drain and 24-inch Waterlines
Project
Description
Phase 1 of this project is for the installation of storm drains
and 24" diameter waterlines in 91st Avenue from Union Hills
Drive to Beardsley Road and in Beardsley Road from 87th Avenue
to Lake Pleasant Road. Modifications to the existing
basins adjacent to Beardsley Road will be constructed and
re-landscaped.
Additionally, in phase 2, there will be pavement restoration of
91st Avenue from Union Hills Drive to Beardsley Road and for Beardsley Road from
83rd Avenue to 95th Avenue. The subsequent Beardsley Road Project
will address the remaining restoration from 95th Avenue and
Lake Pleasant Road.
The City
of Peoria is proposing to utilize the American Recovery and Reinvestment Act
(ARRA) funding for the pavement restoration from 83rd Avenue to
95th Avenue
Click here to learn more about the water line Improvement
portion of this project.
Project at a Glance
|
Lead Agency |
City of Peoria
Burton Charron, P.E. (Project Manager)
Phone: 623-773-7237
E-mail: Burton.charron@PeoriaAz.gov |
|
Construction
Manager |
City of Peoria
Geoffrey Zinnecker, P.E.
Phone: 623-773-7293
E-mail: Geoffrey.zinnecker@PeoriaAz.gov |
|
Design Consultant |
Entellus \ Brooks
Strand Associates |
|
Contractor |
Pulice
Construction |
|
Project Budget |
$11 Million |
|
Funding Sources |
-
General
Obligation Bonds
-
Water Revenue
Bonds
-
Water Expansion
Fees
-
Water Utility
Fees
|
Project
Status
Construction is proposed to begin in May
2009 and proposed to be completed in the Summer 2010.
Utility relocation work has commenced and will continue to be
ongoing through construction.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
0% |
|
Download
Documents
Last
Updated:
Tuesday June 30, 2009 02:50 PM
|