The City of Peoria has completed
a study of the intersection and determined that a signal is
warranted at 95th Avenue and Lake Pleasant Parkway. This
project is to design the signalization of the intersection as
well as connect to an Intelligent Transportation System that is
being expanded within the City of Peoria. The project will
follow the construction of the project as quickly as possible.
Project at a Glance
|
Lead Agency |
City of Peoria
Geoffrey Zinnecker (Peoria Project Manager)
Phone: 623-773-7293
E-mail:
Geoffrey.zinnecker@PeoriaAz.Gov |
|
Design Consultant |
AMEC |
|
Contractor |
CS, Construction,
Inc. |
|
Project Budget |
$400,000.00 |
|
Funding Sources |
General
Obligation Bonds |
Project Status Schedule
Present the project to City Council on July 1, 2008.
Finish construction in the winter, 2008.
|
Design |
95% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
0% |
|