DEER VALLEY ROAD REPAIR, 83rd AVENUE TO HILLCREST BOULEVARD (PW01005)

Project Description
A portion of Deer Valley Road pavement is failing under the heavy traffic that has been added to the road since it was constructed.  The north lane and parts of the adjacent lane, which were constructed when the area was in the County, are failing along the section of the road from Hillcrest Boulevard west to 83rd Avenue.  This project calls for the removal of the thin section of pavement and a complete rebuilding of that area.  The new section will conform to the City of Peoria standards for arterial roadways.

Project at a Glance

Lead Agency City of Peoria
Geoffrey Zinnecker (Peoria Project Manager)
Phone: 623-773-7293
E-mail:
Geoffrey.zinnecker@Peoriaaz.gov
Design Consultant In-House
Contractor J. Banicki Construction, Inc.
Project Budget $500,160.00
Funding Sources

GO Bonds

Proposed General Obligation Bonds

Project Status Schedule

The project design is 100% complete. Construction of the roadway repair is to be completed by March 2010. 

Design 100%
25% 50% 75% 100%

 

                                     
Construction 75%
25% 50% 75% 100%

 

                                     

Links

Updated: February 17, 2010

 