|
ARRA Pavement
Preservation Project
 |
Project
Description
|
|
The American Recovery and Reinvestment Act (ARRA) Pavement
Preservation Project will restore the pavement surface and
incorporate bike lanes for several roadway segments prioritized
in a list below. Arizona Department of Transportation (ADOT) is
responsible for administering the City of Peoria’s ARRA
program. ADOT has selected AMEC Earth and Environmental to
administer the program on their behalf. This Pavement
Preservation Project is being conducted in this manner in the
interest of facilitating the necessary federal regulatory
requirements to appropriately qualify the project for ARRA funding. |
Project at a Glance
|
Lead Agency |
Arizona Department
of Transportation (ADOT)
Jeffrey Miles
Phone:
602-712-8336 |
|
Partner Agency |
City of Peoria
Burton Charron (Peoria Project Manager)
Phone: 623-773-7237
E-mail:
Burton.Charron@PeoriaAz.Gov |
|
Design Consultant |
AMEC |
|
Contractor |
N/A |
|
Project Budget |
$1.2M |
|
Funding Source: |
Federal ARRA
Stimulus |
Project
Status
ADOT is in
the process of defining the scope of work for the Peoria
Projects and ordering AMEC to commence the design and project
administration. Maricopa Association of Governments has also
acknowledged the City’s Pavement Preservation Projects for
inclusion into the Regional Transportation Improvement Plan,
this being a necessary step to initially qualify the project.
The National Environmental Policy Act (NEPA) process has been
initiated for the Pavement Preservation Projects.
|
Design |
0% |
|
|
Land
Acquisition |
NA |
|
|
Construction |
0% |
|
Project Priority and Phases:
Design Phase will
commence in September 2009 and complete by November 2009. Bidding
will be conducted between December 2009 and April 2010.
Construction Phase will
be scheduled between May 2010 to September 2010, when the pavement
surface temperature conditions are within specifications.
The order of priority
for construction phasing will be as follows:
Beardsley Road
from 83rd Avenue to 99th Avenue
91st
Avenue from Union Hills Drive to Beardsley Road
83rd
Avenue from Union Hills Drive to Village Parkway
Lake Pleasant
Road from Beardsley Road to Rose Garden Lane
83rd
Avenue from Deer Valley Road to Lake Pleasant Parkway
Last
Updated:
Monday August 17, 2009 04:03 PM
|