|
ARRA PAVEMENT PRESERVATION PROJECT (EN00315)
|
|
Financed
by the
American Recovery and Reinvestment Act (ARRA) |
 |
|
The American Recovery and Reinvestment Act (ARRA) Pavement
Preservation Project will restore the pavement surface and
incorporate bike lanes for several roadway segments prioritized
in a list below. The Arizona Department of Transportation (ADOT) is
responsible for administering the City of Peoria’s ARRA
program. ADOT has selected AMEC Earth and Environmental to
administer the program on their behalf. This Pavement
Preservation Project is being conducted in this manner in the
interest of facilitating the necessary Federal regulatory
requirements to appropriately qualify the project for ARRA funding. |
Project at a Glance
|
Lead Agency |
Arizona Department
of Transportation (ADOT)
Jeffrey Miles
Phone:
602-712-8336 |
|
Partner Agency |
City of Peoria
Burton Charron (Peoria Project Manager)
Phone: 623-773-7212
E-mail:
Burton.Charron@Peoriaaz.gov |
|
Design Consultant |
AMEC |
|
Contractor |
Construction 70 |
|
Project Budget |
$2.5M |
|
Funding Source: |
Federal ARRA
Stimulus |
Project
Status
ADOT hired AMEC
for the design and project
administration. Maricopa Association of Governments
has also
acknowledged the City’s Pavement Preservation Projects for
inclusion to the
Regional Transportation Improvement Plan,
which is a necessary step to initially qualify the project.
The National Environmental Policy Act (NEPA)
process has been approved, along with all other
approval processes in order to implement the Pavement
Preservation Projects.
|
Design |
100% |
|
|
Land
Acquisition |
NA |
|
|
Construction |
95% |
|
Project Priority and Phases:
Design Phase and bidding
are complete.
Construction commenced June 2010, and
continued through August 2010. All paving has been completed.
Video detection has been completed. Permanent pavement markings remain to be completed.
The list of roadways
that have been improved are as follows:
Beardsley Road,
from 83rd Avenue to 99th Avenue
91st
Avenue, from Union Hills Drive to Beardsley Road
83rd
Avenue, from Union Hills Drive to Village Parkway
Lake Pleasant
Road, from Beardsley Road to Rose Garden Lane
83rd
Avenue, from Deer Valley Road to Lone Cactus Drive
Updated August 26, 2010
|