ARRA Pavement Preservation Project

Project Description
 
The American Recovery and Reinvestment Act (ARRA) Pavement Preservation Project will restore the pavement surface and incorporate bike lanes for several roadway segments prioritized in a list below. Arizona Department of Transportation (ADOT) is responsible for administering the City of Peoria’s ARRA program.  ADOT has selected AMEC Earth and Environmental to administer the program on their behalf. This Pavement Preservation Project is being conducted in this manner in the interest of facilitating the necessary federal regulatory requirements to appropriately qualify the project for ARRA funding.

 

Project at a Glance

Lead Agency

Arizona Department of Transportation (ADOT)

Jeffrey Miles

Phone: 602-712-8336

Partner Agency

 

City of Peoria
Burton Charron (Peoria Project Manager)
Phone: 623-773-7237
E-mail:
Burton.Charron@PeoriaAz.Gov
Design Consultant AMEC
Contractor N/A
Project Budget $1.2M
Funding Source:

Federal ARRA Stimulus

 

Project Status
ADOT is in the process of defining the scope of work for the Peoria Projects and ordering AMEC to commence the design and project administration.  Maricopa Association of Governments has also acknowledged the City’s Pavement Preservation Projects for inclusion into the Regional Transportation Improvement Plan, this being a necessary step to initially qualify the project.  The National Environmental Policy Act (NEPA) process has been initiated for the Pavement Preservation Projects.

 

Design 0%
25% 50% 75% 100%

 

                                     
Land Acquisition NA
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     

 

Project Priority and Phases:

Design Phase will commence in September 2009 and complete by November 2009.  Bidding will be conducted between December 2009 and April 2010.

 

Construction Phase will be scheduled between May 2010 to September 2010, when the pavement surface temperature conditions are within specifications.

 

The order of priority for construction phasing will be as follows:

          Beardsley Road from 83rd Avenue to 99th Avenue

          91st Avenue from Union Hills Drive to Beardsley Road

          83rd Avenue from Union Hills Drive to Village Parkway

          Lake Pleasant Road from Beardsley Road to Rose Garden Lane

          83rd Avenue from Deer Valley Road to Lake Pleasant Parkway

 

 

 