|
91st
AVENUE AND OLIVE AVENUE INTERSECTION IMPROVEMENTS (PW00245)
Project
Description
This project
includes design, ROW, construction, and construction
administration for the capacity
improvements to the intersection and vicinity to accommodate
additional turn lanes (both right and left), and additional
through lanes determined through an analysis and projection of
traffic data. Improvements will include: paving, curb, gutter,
driveways, medians, pavement marking, signing and striping,
traffic signal, street lighting, sidewalks, pedestrian access
ramps, landscaping, landscape irrigation and utility
relocations.
Project at a Glance
|
Lead Agency |
Arizona
Department of Transportation (ADOT)
|
|
Partner Agency |
City of Peoria
Ben Wilson (Project Manager)
Phone: 623-773-7185
E-mail: Ben.Wilson@Peoriaaz.gov |
|
Design Consultant |
Kimley-Horn &
Associates |
|
Contractor |
N/A |
|
Project Budget |
$4 Million |
|
Funding Sources |
$3.2 Million
Federal Congestion Mitigation and Air Quality Funds (CMAQ)
$150,000
General Obligation Bonds |
Project Status
The City of Peoria
submitted a Federal Fiscal Year 2009 close-out application
to the Maricopa Association (MAG) for region Federal funds.
As a result of the application, the
project
advertisement was placed on hold,
waiting for the potential MAG close-out funds. The City
has successfully been granted an additional $2.5M in Federal
Congestion Mitigation and Air Quality (CMAQ) funds. The
total Federal money granted to this project is $3.2M. The widening
project by ADOT was advertised December 22, 2009, and the ADOT
contractor is anticipated to begin in March 2010, and
have a six month construction duration.
Utility
relocations have been completed.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
25% |
|
Links
Updated February 19,
2010
|