|
91st
Avenue and Olive Avenue Intersection Improvements
Project
Description
This project
includes design, ROW, construction, and construction
administration in two phases for interim and ultimate capacity
improvements to the intersection and vicinity to accommodate
additional turn lanes (both right and left), and additional
through lanes determined through an analysis and projection of
traffic data. Improvements will include: paving, curb, gutter,
driveways, medians, pavement marking, signing and striping,
street lighting, sidewalks, pedestrian access ramps,
landscaping, landscape irrigation and utility relocations. The
traffic signal will be relocated and modified to direct
additional turn lanes and thru lanes. Traffic signal
interconnect conduit and related facilities will be included in
the project.
Project at a Glance
|
Lead Agency |
Arizona
Department of Transportation (ADOT)
|
|
Partner Agency |
City of Peoria
Ben Wilson (Project Manager)
Phone: 623-773-7185
E-mail: Ben.Wilson@PeoriaAz.gov |
|
Design Consultant |
Kimley-Horn &
Associates |
|
Contractor |
N/A |
|
Project Budget |
$3.7 Million |
|
Funding Sources |
General Obligation
Bonds |
Project Status as of
December 2008
The
widening project is anticipated to start in the Spring, 2009.
Utilities, such as SRP Irrigation, SRP Power, APS Power,
Southwest Gas and Cox Communications will be relocated during
the year, 2008. These utilities need to be relocated before the
widening construction can occur.
There will
be on-and-off construction activities beginning from July 2008
through February 2009 prior to the intersection pavement widening.
Lane restrictions will be limited to night-time when possible.
Agreement with ADOT
to administer construction was approved by City Council on December 2,
2008. Approval allows ADOT to advertise for the
intersection widening construction anticipated for Spring 2009.
|
Activity
|
Anticipated Activity Duration |
|
Progress of Activity
|
|
Intersection Widening Design |
Completing Design Documents for submittal to ADOT |
100% |
|
|
COX relocations |
Relocated as of April 2008 |
100% |
|
|
Activities
above must be completed before Activities below can start |
|
Southwest Gas relocation |
Expect relocation to be completed by October 10, 2008 |
100% |
|
|
Land Acquisition |
Finalizing Land Acquisition |
99% |
|
|
City waterline relocations |
Anticipated relocations
are completed |
100% |
|
|
Activities
above must be completed before Activities below can start |
|
SRP Power relocation |
Anticipate
relocation work in December 2008 to January 2009 |
0% |
|
|
APS Power relocation |
APS has
relocated
No lane
restrictions expected |
100% |
|
|
Activities
above must be completed before Activities below can start |
|
SRP Irrigation relocation |
Relocation has begun. Work is expected to continue through
February 2009. Please expect traffic delays. |
0% |
|
|
Activities
above must be completed before Activities below can start |
|
Intersection Widening Construction |
April 2009 to December 2009 |
0% |
|
Download
Documents
Last
Updated:
Wednesday December 17, 2008 12:04 PM
|