Building Peoria logo

Building Peoria Home   I   Major Projects List   I  Road Closures

City Construction FAQ   I   Construction Lingo   I   Links

 91st AVENUE AND OLIVE AVENUE INTERSECTION IMPROVEMENTS (PW00245)

Project Description
This project includes design, ROW, construction, and construction administration for the capacity improvements to the intersection and vicinity to accommodate additional turn lanes (both right and left), and additional through lanes determined through an analysis and projection of traffic data.  Improvements will include: paving, curb, gutter, driveways, medians, pavement marking, signing and striping, traffic signal, street lighting, sidewalks, pedestrian access ramps, landscaping, landscape irrigation and utility relocations. 

Project at a Glance

Lead Agency

Arizona Department of Transportation (ADOT)

Resident Engineer - Alfred Zuniga

520-326-8195

Partner Agency City of Peoria
Ben Wilson (Project Manager)
Phone: 623-773-7185
E-mail: Ben.Wilson@Peoriaaz.gov
Design Consultant Kimley-Horn & Associates
Contractor Combs Construction
Project Budget $4 Million
Funding Sources $3.2 Million     Federal Congestion Mitigation and Air Quality Funds (CMAQ) $150,000        General Obligation Bonds

Project Status
The City of Peoria submitted a Federal Fiscal Year 2009 close-out application to the Maricopa Association (MAG) for region Federal funds.  As a result of the application, the project advertisement was placed on hold, waiting for the potential MAG close-out funds.  The City has successfully been granted an additional $2.5M in Federal Congestion Mitigation and Air Quality (CMAQ) funds.  The total Federal money granted to this project is $3.2M.  The construction duration will be from April 2010 through December 2010. Paving is completed. The final thermoplastic striping has been placed.  Landscaping is now complete.  Barricades in the intersection are due to the ADOT work under Loop 101.

Design 100%
25% 50% 75% 100%
                                       
Land Acquisition 100%
25% 50% 75% 100%

 

                                     
Construction 95%
25% 50% 75% 100%

 

                                     

Links

Updated December 22, 2010