Project Description
This project is for the installation of a traffic signal at the intersection, along with sidewalk ramp improvements as needed.  The project will consist of the installation of the traffic signal and incidental sidewalk ramp installations for the remaining crossings.  Right-of-way will be needed which will include fence relocations and landscape restoration.

Project at a Glance

Lead Agency City of Peoria
Ben Wilson (Project Manager)
Phone: 623-773-7185
E-mail: Ben.Wilson@PeoriaAz.gov
Design Consultant
Parsons Brinckerhoff
Doug LaMonte
480-966-8295
Contractor N/A
Project Budget $500,000
Funding Sources

Intersection Zone 1 Development Fee Street System Account

Project Status
The project plans have been finalized.  Construction has started and should continue through April, 2008.

Design 100%
25% 50% 75% 100%

 

                                     
Land Acquisition 100%
25% 50% 75% 100%

 

                                     
Construction 75%
25% 50% 75% 100%

 

                                     