87th Avenue; Olive Avenue to Hatcher Road
Project Description
This project is to provide for the
design, construction, and right-of-way acquisition required to
widen the west half of 87th Avenue between Olive
Avenue and Hatcher Road. This will include pavement, storm
drainage, curbs, gutters, driveways and sidewalk improvements. Pavement widening will
provide for one lane in each direction with a center two-way
left turn lane and bike lanes. No additional widening of
87th Avenue is
anticipated on the east side of the road adjacent to the
existing subdivision, however; pavement repairs/resurfacing will
likely occur. In addition, this project will construct a
48-inch diameter regional drainage pipe along 87th
Avenue from Olive Avenue extending north to just beyond Hatcher
Road where it will be plugged for future extension to Mountain
View Road. This drainage pipe will not only provide future
regional drainage benefits to the Old Town Peoria vicinity, but
will provide the needed immediate drainage improvement to help
mitigate current nuisance storm drain ponding occurring at the
southwest corner of Hatcher Road and 87th Avenue.
Additional street lighting is not anticipated at this time as
existing lighting improvements along this stretch of roadway
currently meets the City of Peoria guidelines.
Project at a Glance
|
Lead Agency |
City of Peoria
Richard Costa (Peoria Project Manager)
Phone: 623-773-7951
Email:
Richard.Costa@peoriaaz.gov |
|
Design Consultant |
Kimley-Horn
|
|
Contractor |
J. Banicki
Construction |
|
Project Budget |
$1.8 Million |
|
Funding Sources |
Transportation
Sales Tax |
Project
Status
The project
construction is
99% complete. Remaining items include additional striping
work which is anticipates to be complete by the end of November.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
99% |
|