 83rd Avenue Widening; Williams Road to Calle Lejos Road

Project Description
The City of Peoria (City) is working to complete the street improvements at 83rd Avenue between Williams Road and Calle Lejos Road.  The City will be widening the current three-lane configuration to a five-lane configuration.  In addition, improvements to the 83rd Ave & Pinnacle Peak Intersection will happen in conjunction with the widening to included dual lefts for north bound and south bound traffic.

Project at a Glance

Lead Agency City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7260
E-mail: Karl.Zook@PeoriaAz.gov
Design Consultant PB America
Contractor To Be Determined
Project Budget $7,251,000
Funding Sources
  • General Obligation Bonds

  • Proposed General Obligation Bonds

Project Status
The project design is 40% complete, and is scheduled for construction in Summer 2009.  Coordination with the utility companies has commenced; actual utility relocation is scheduled to take place between January 2009 and June 2009

Design 40%
25% 50% 75% 100%

 

                                     
Land Acquisition 5%
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     