83RD AVENUE; NORTHERN AVENUE TO MOUNTAIN VIEW
ROAD
Project
Description
This project will widen and/or reconstruct 83rd Avenue, from
Butler Drive to Olive Avenue, to include two lanes in
each direction, bike lanes and a raised landscaped median.
In addition, Butler Drive will be
partially improved from 79th Avenue to 83rd Avenue to include a
single lane in each direction. Additional improvements to
Butler Drive will be completed by future developers.
Additional waterline improvements are also being considered
along 83rd Avenue, from Butler Drive to Mountain View Road, and
along Butler Drive. This project will be coordinated with
the planned City of Peoria Community Park No. 2, which will be
located at the southeast corner of 83rd Avenue and Olive Avenue.
Finally, with this project, the City of Peoria intends to annex
this segment of 83rd Avenue (Butler Drive to Olive Avenue), from the County (roadway right-of-way only)
to the City.
Project at a Glance
|
Lead Agency |
City of Peoria
Richard Costa (Project Manager)
Phone: 623-773-7951
E-mail: Richard.costa@Peoriaaz.gov |
|
Design Consultant |
To Be Determined |
|
Contractor |
To Be Determined |
|
Project Budget |
$6.5 Million |
|
Funding Source |
-
Water and
Wastewater Utility Fees
-
Transportation
Sales Tax
-
County
Transportation Tax
-
Streets Zone 1
Development Fees
-
General
Obligation Bonds
-
Proposed General
Obligation Bonds
|
Project
Status
The City is currently in negotiations with the
selected design consultant on a design contract.
Anticipating award of design contract in April/May 2010.
Construction could begin early 2010 and end in early 2011.
|
Design |
0% |
|
|
Land
Acquisition |
0% |
|
|
Construction |
0% |
|
Links
Updated February 12,
2010
|