Project Description
The City of Peoria (City) has completed the majority of the intersection widening improvements at 83rd Avenue and Deer Valley Road.  The City has constructed new right turn lanes, left turn lanes, applied a surface treatment and re-striped the intersection and 83rd Avenue between Deer Valley Road and Williams Road.  This project is being coordinated with the widening of Deer Valley Road between 91st Avenue and 83rd Avenue.

Project at a Glance

Lead Agency City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7260
E-mail: Karl.Zook@PeoriaAz.gov
Design Consultant Premier Engineering
Contractor Achen-Garnder Engineering, LLC
Project Budget $2,786,948
Funding Sources
  • General Obligation Bonds

  • Proposed General Obligation Bonds

Project Status
The project design is 100% complete, and construction will be completed in January, 2009.  Coordination with the utility companies is complete.

Design 100%
25% 50% 75% 100%

 

                                     
Land Acquisition 100%
25% 50% 75% 100%

 

                                     
Construction 100%
25% 50% 75% 100%

 

                                     