Building Peoria logo

Building Peoria Home   I   Major Projects List   I  Road Closures

City Construction FAQ   I   Construction Lingo   I   Links

 83rd Avenue and Deer Valley Road Intersection Improvements

Project Description
The City of Peoria (City) is working to complete the street improvements at the 83rd Avenue and Deer Valley Road intersection.  The City will be adding new right turn lanes and additional left turn lanes to accommodate the new widening of Deer Valley Road between 91st Avenue and 83rd Avenue.

Project at a Glance

Lead Agency City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7260
E-mail: Karl.Zook@PeoriaAz.gov
Design Consultant Premier Engineering
Contractor N/A
Project Budget $2,786,948
Funding Sources
  • General Obligation Bonds

  • Proposed General Obligation Bonds

Project Status
The project design is complete, and is scheduled for construction in September 2007.  Coordination with the utility companies is near completion; actual utility relocation will commence in mid to late March 2007 and will be completed September 2007.

Design 75%
25% 50% 75% 100%

 

                                     
Land Acquisition 80%
25% 50% 75% 100%

 

                                     
Construction 0%
25% 50% 75% 100%

 

                                     

Download Documents

 

Last Updated: Friday May 30, 2008 11:39 AM

 