The City of Peoria (City) is working to complete the street
improvements at the 83rd Avenue and Deer Valley Road
intersection. The City will be adding new right turn lanes
and additional left turn lanes to accommodate the new widening
of Deer Valley Road between 91st Avenue and 83rd Avenue.
Project at a Glance
|
Lead Agency |
City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7260
E-mail: Karl.Zook@PeoriaAz.gov |
|
Design Consultant |
Premier
Engineering |
|
Contractor |
N/A |
|
Project Budget |
$2,786,948 |
|
Funding Sources |
|
Project
Status
The project design is complete, and is scheduled
for construction in September 2007. Coordination with the
utility companies is near completion; actual utility relocation
will commence in mid to late March 2007 and will be completed
September 2007.
|
Design |
75% |
|
|
Land
Acquisition |
80% |
|
|
Construction |
0% |
|