Project
Description
The City of Peoria (City) has completed the majority of the
intersection widening improvements at 83rd Avenue and Deer
Valley Road. The City has constructed new right turn
lanes, left turn lanes, applied a surface treatment and
re-striped the intersection and 83rd Avenue between Deer Valley
Road and Williams Road. This project is being coordinated
with the widening of Deer Valley Road between 91st Avenue and
83rd Avenue.
Project at a Glance
|
Lead Agency |
City of Peoria
Karl Zook (Project Manager)
Phone: 623-773-7260
E-mail: Karl.Zook@PeoriaAz.gov |
|
Design Consultant |
Premier Engineering |
|
Contractor |
Achen-Garnder
Engineering, LLC |
|
Project Budget |
$2,786,948 |
|
Funding Sources |
|
Project
Status
The project design is 100% complete, and construction
will be completed in January, 2009. Coordination with the
utility companies is complete.
|
Design |
100% |
|
|
Land
Acquisition |
100% |
|
|
Construction |
100% |
|
Download
Documents
Last
Updated:
Wednesday September 02, 2009 01:42 PM
|