Building Peoria Home   I   Major Projects List   I  Road Closures

City Construction FAQ   I   Construction Lingo   I   Links

 
Skunk Creek Trail

Project Description
Construction of a trail segment connecting New River (under Loop 101) and 83rd Ave (Skunk Creek).

Background
The City of Peoria was awarded a federal Congestion Mitigation Air Quality (CMAQ) project for fiscal year 2007 to provide a trail connection from New River to the Skunk Creek with underpasses located at  Loop 101 and at 83rd Avenue.
 

Project at a Glance

Lead Agency City of Peoria
Community Services Department, Parks Division
Phone: 623-773-7137
E-mail:
parks@peoriaaz.gov
Partner Agency

Arizona Department of Transportation (ADOT)

Contractor TBD
Project Budget $1.3 million
Funding Source Development Fees, Bonds, and Federal Funds

Project Status
The design of the underpass that connects to Rio Vista Park to the residents of the east side of the Loop 101 is complete. Coordination efforts with the Arizona Department of Transportation are in progress to put the project to bid. It is anticipated construction will start early in fall 2008, with completion targeted for the end of the calendar year.

Design  
25% 50% 75% 100%

 

                                     
Land Acquisition  
25% 50% 75% 100%

 

                                     
Construction  
25% 50% 75% 100%

 

                                     

 

Last Updated: Wednesday May 28, 2008 09:34 AM

 

Copyright © 2006 City of Peoria - All Rights Reserved