|
Community Park Number 2
Project
Description
Construction of an 80 acre community park located at the southeast corner of 83rd
Avenue and Olive.
Project at a Glance
|
Lead Agency |
City of Peoria
Community Services Department, Parks Division
Phone: 623-773-7137
E-mail:
parks@peoriaaz.gov |
|
Partner Agency |
N/A
|
|
Contractor |
Haydon Contracting
|
|
Project Budget |
$7.8 million |
|
Funding Source |
Bonds and
Half-Cent Sales Tax |
Project
Status
The master plan can be viewed via the attached
link below. This master plan alternative was built on a
series of public meetings and feedback from stakeholder
meetings. The next steps include completion of the site
plan and completion of the design documents, which will occur
over the next year. This project will be coordinated
with street and drainage improvements on 83rd Avenue between
Mountain View and Butler Road as to minimize disruption to
adjacent neighborhoods.
|
Design |
|
|
|
Land
Acquisition |
|
|
|
Construction |
|
|
Click
here to view the preferred alternative
Last
Updated:
Friday June 05, 2009 09:52 AM
|